PROJECT TITLE

RICKARD RD DRAINAGE UPGRADE, BANKSTOWN

LOCATION

Rickard Road, Bankstown

BUDGET

$1.0m - $1.1m

DURATION

16 Weeks, Commencement June 2020

SERVICES

Earthworks, Demolition, Stormwater Drainage & Channel Stabilisation

SECTOR

Government

about

The upgrade of the stormwater drainage system along Rickard Road

J Group was engaged by Bankstown City Council for the upgrade of the stormwater drainage system along Rickard Road. The project includes realigning the kerb and gutter, reconstructing commercial crossings, and constructing in-situ stormwater pits to improve drainage capacity. Additionally, the works involve pavement reconstruction, line marking, minor landscaping, and the relocation of water mains.

Situated in a high-traffic commercial area, the project requires careful coordination with strict traffic management plans and environmental controls to ensure minimal disruption to local businesses and road users. Night work was permitted with restrictions on noise, and the project plays a crucial role in enhancing the drainage infrastructure to prevent future flooding and erosion.

THE SCOPE

• Site Establishment: Setting up the site with temporary fencing, traffic control measures, and site facilities.

• Demolition: Removal and disposal of existing kerbs, gutters, drainage pits, and stormwater pipes.

• Stormwater Drainage: Construction of in-situ stormwater pits and installation of new stormwater pipes to improve drainage capacity and prevent flooding.

• Kerb and Gutter Realignment: Reconstruction of kerbs, gutters, and commercial crossings for proper drainage flow.

• Pavement Works: Reconstruction of road pavements and footpaths in line with new design levels.

• Water Main Relocation: Relocation of water mains to accommodate the new drainage system.

• Traffic Management: Minimise disruptions in this high-traffic commercial area, including obtaining a Road Occupancy License (ROL).

ADDITIONAL WORKS

results

Improved stormwater management reducing flood and erosion risk

The Rickard Road Drainage Upgrade resulted in enhanced stormwater management, effectively reducing the risk of flooding and erosion. The realignment of kerbs and gutters, along with pavement reconstruction, greatly improved traffic flow and safety in the area. By implementing efficient traffic management, disruptions to local businesses and road users were minimized throughout the project. The work ensured full environmental compliance, utilizing erosion and sediment controls to protect the surroundings. Additionally, the project added visual improvements through landscaping efforts, contributing to a safer and more reliable drainage system for the community.

contact

Ready to build tomorrow’s infrastructure?

Get in touch